BBWO Programme Progress Review 2005 Issue 1.0 January -
December 2005
Jump To:
The Welsh Assembly Government's
Broadband Wales Programme was launched in July 2002. The aim
was to improve the availability, affordability and take-up of
broadband across Wales.
A strategic review undertaken during 2004 confirmed that of
the eight original targets, four had already been met. Others were
on schedule to be achieved before 2007 and others were deemed less
relevant in view of the advances in the telecommunications market.
As a result of these findings, a new broadband strategy for Wales
was developed. The strategy for 2005-2007 was launched in January
2005.
At the end of 2005, the Broadband Wales Observatory
(BBWO) undertook an independent review of the progress made
against seven of the seventeen targets due for completion. The
review confirmed that European Commission (EC) State Aid issues
continue to impact on the delivery of some of projects. However,
the programme is within agreed 'tolerances' and is on schedule to
achieve the majority of targets published in the Broadband Wales
Programme Strategy 2005-2007.
Note:
The Broadband Wales Programme (BBW) is managed to the
standards outlined by the Office of Government and Commerce (OGC)
in Managing Successful Programmes (MSP). All BBW projects comply
with the project management principles outlined by OGC in
Prince2.
Broadband Definition
For the purposes of the Broadband Wales Programme asymmetric
speeds of 512kbps to 2Mbps downstream (i.e. to the customer) and
256kbps to 512kbps upstream (i.e. from the customer) are considered
as first generation or mass market
broadband.
Bandwidth between 2Mbps and 10Mbps is deemed to be
second generation broadband. This includes
asymmetrical speeds between 2Mbps and 10Mbps downstream and 512kbps
and 1Mbps upstream as well as symmetrical speeds (where upstream
and downstream speeds are equal).
Very high speed broadband (10Mbps and over symmetrical) is
defined as
fibre speed.
|
Target
|
By the end of 2005 the Broadband Wales
Programme will:
|
|
1
|
Ensure that take-up of first generation
broadband in Wales is at least equal to the UK average
|
|
2
|
Ensure that everyone in Wales has access to
information that allows them to make a decision on what broadband
could mean for them
|
|
3
|
Award a contract to allow homes, businesses and
voluntary sector sites in Wales to have access to first generation
broadband infrastructure
|
|
4
|
Issue at least a thousand Business Support
Scheme Grants to SMEs and voluntary sector organisations in
Wales
|
|
5
|
Create a fund to support the provision of
broadband to public sector sites in Wales
|
|
6
|
Develop an agreed Welsh policy for the
aggregation of public sector demand for broadband
infrastructure
|
|
7
|
Demonstrate to the telecommunications industry
the level of demand for second generation broadband infrastructure
that exists in Wales
|
|
Ref.
|
During 2006 the Broadband Wales
Programme will:
|
|
8
|
Fund two Advisers in each Local Authority in
Wales to help implement local broadband strategies (until March
2006)
|
|
9
|
Fund a resilient broadband network linking all
22 Local Authorities in Wales, supporting mission critical and
value added applications (until July 2006)
|
|
10
|
Announce and implement the agreed policy in
respect of the aggregation of public sector demand for broadband
infrastructure
|
|
11
|
Ensure that take-up of first generation
broadband in Wales is at least equal to the UK average
|
|
Ref.
|
By March 2007 the Broadband Wales
Programme will:
|
|
12
|
Aim to support at least 50 local projects
throughout Wales
|
|
13
|
Ensure the availability of second generation
broadband infrastructure to at least 50% of the Welsh business
population
|
|
14
|
Aim to secure the provision of fibre speed
broadband connectivity at pre-identified business parks / locations
at affordable prices
|
|
15
|
Aim to ensure that Wales has extensive
geographic access to competitive wholesale infrastructure
|
|
16
|
Implement an agreed strategy in relation to the
provision of a direct connection from Wales to the global core
internet
|
|
17
|
Increase international awareness of the
Broadband Wales Programme benefits to help enhance Wales'
reputation as a place for businesses to locate and grow
|
This document aims to provide a succinct review of the
progress made towards achieving the first seven of these seventeen
strategic targets.
The key findings of the progress review undertaken by the
Broadband Wales Observatory (BBWO) are outlined below.
Strategic Target 1
"Ensure that take-up of first generation broadband in
Wales is at least equal to the UK average"
The broadband market continued to show positive signs of
development during the review period; with significant growth
reflecting the growing popularity, affordability and widespread
availability of broadband across Wales. From the variety of
information sources available, BBWO estimates that the 'gap'
between take-up levels in Wales and the rest of the UK has
narrowed; down from over three percentage points in 2004 to less
than two percentage points during the latter half of 2005.
- Market analysts estimate that there were 9.8 million broadband
connections in the UK at the end of 2005; with xDSL
broadband accounting for 6.7 million connections and cable modem
broadband accounting for the majority of the remainder.
- In terms of take-up, 9.8 million broadband connections in the
UK is equal to 39% of UK homes and businesses having access to the
internet via a broadband connection or 16 broadband connections per
100 people (i.e. 16% of the UK population).
- Whilst detailed figures are not available for December 2005,
there is likely to be little change in the rankings of individual
countries compared with June 2005. At that time, OECD ranked the UK
5th in terms of market size (behind USA, Japan, South
Korea and Germany). In terms of broadband penetration, the UK
ranked 13th out of the 30 OECD countries.
- BBWO estimates that there were less than 500,000 broadband
connections in Wales at the end of 2005; with xDSL broadband
accounting for up to 350,000 connections and cable modem broadband
accounting for the majority of the remainder.
- In terms of take-up, 500,000 broadband connections in Wales is
equal to 35% of the homes and businesses having access to the
internet via a broadband connection or 16 broadband connections per
100 people (i.e. 16% of the population of Wales).
·
- When compared with published data for the third quarter of
2005, BBWO estimates that there were 15 broadband connections per
100 inhabitants (i.e. 15% of the population) in both Wales[1] and in
the UK[2].
These calculations place take-up of broadband across Wales in
line with the average for the UK. The calculations for Wales are
validated by a survey
[3] commissioned by the Welsh Assembly Government's
Broadband Wales Unit.
- 71% of all respondents had a PC at home
- 63% of all respondents had access to the internet at home
- 32%[4] of all respondents had access to the internet at
home via a broadband connection[5]
Take up of PC, Internet and Broadband by Local Authority
Figure 1 - WAG BBW Commissioned Residential
Survey, ORC International, October 2005
The survey revealed the highest proportion of broadband
households was in the Vale of Glamorgan; whilst the lowest
proportion was in Anglesey.
The disparity in take-up levels may be linked to the length of
time that mass market broadband has been available within each of
the Local Authority (LA) areas. Equally, the disparity may be due
to the socio demographic profile – in terms of age, income and
employment status - of the LA. Initial analysis of the key findings
from the survey suggests that both explanations are too simplistic.
Further research may be required to better understand the drivers
and barriers to increased take-up of broadband.
Meanwhile, with over 95% of all sites able to access first
generation broadband since mid 2005, it will be interesting to
continue monitoring broadband penetration levels in Wales and the
UK.
Strategic Target 2
"Ensure that everyone in Wales has access to information
which allows them to make a decision on what broadband could mean
for them"
Progress Review
The Broadband Wales Programme implemented a PR and marketing
programme throughout 2005 with the aim of helping to achieve
strategic targets 1, 2, and 3. The activities were
specifically designed:
a)To raise awareness of broadband and of the Welsh Assembly
Government's Broadband Wales Programme.
b)To demonstrate to targeted groups the features, advantages
and benefits to be gained from the use of broadband.
c)To encourage potential broadband users in 'blackspot areas'
to register their requirements via the Broadband Brokerage Scheme
(www.bbwo.org.uk).
The main activities undertaken by BBW during the year
included:
- Media relations - in support of individual BBW Projects.
- Advertising in local and national press - included local radio,
street (48 sheet posters) and train station billboards and
buses.
- Banner advertising placed on third party websites - included
MSN, Hotmail, Google plus Local Authorities, Assembly Sponsored
Public Bodies (ASPBs) and other BBW partner'
websites.
- Mail-shot - 10,000 households located within reach of the 35
commercially unviable telephone exchange areas in Wales plus a
further 650,000 homes and 16,000 businesses located (in 100,000
targeted postcodes areas) across Wales.
- 'Get Smart: Get Broadband' road-show - supported local and
regional events across Wales.
- Broadband technology booklets - distributed to target groups
across Wales.
- DVDs highlighting the benefits to be gained from broadband (for
consumers and businesses) – distributed to partners across
Wales.
- School packs developed with National Grid for Learning (NGfL) –
distributed to primary schools across Wales
- 'Taskforce' – team of broadband experts offered advice to
individuals and communities across Wales.
- 'Try Before You Buy Scheme' - supported businesses and ICT
Centres located in each of the Local Authority areas of
Wales
Success was measured against the pre-agreed objectives. For
example, 'campaign closure reports' recorded:
a)The response rate to advertising and direct marketing
activities – including the numbers of 'click throughs' and 'unique
visitors' to websites, the number of registrations on Broadband
Brokerage Scheme and the number of enquiries managed by the
Broadband Wales Observatory.
b)The number of media interviews, the number of positive
headlines generated and the volume of column inches generated in
the targeted press.
c)The number of visitor enquiries managed and broadband
demonstrations given at each event.
Strategic Target 3
"Award a contract to allow homes, businesses and voluntary
sector sites in Wales to have access to first generation broadband
infrastructure"
Progress Review
The Regional Innovative Broadband Support (RIBS) project was
established to achieve strategic target 3. The project is designed
to improve the competitiveness of disadvantaged regions of Wales by
increasing access to broadband in 'not-spot areas'.
The 'not-spot areas' - where potential users are unable to
access a broadband service – include the 35 telephone
exchange areas that the telecommunications providers deem to be
commercially unviable. Other 'not-spot areas' have been identified
by the RIBS project team through the use of the on-line Broadband
Brokerage Scheme (
www.bbwo.org.uk);
established in partnership with the Broadband Wales Observatory at
Cardiff University.
The market was informed of the 'all-Wales' RIBS initiative in
April 2005. The Prior Information Notice (PIN) was issued through
www.buy4wales.co.uk and the Official Journal of the
European Union (OJEU). Requests for further information were
received from 39 organisations and the RIBS project team supplied
the relevant information to allow potential bidders time to
research potential solutions.
On 1st June 2005, the RIBS project gained approval
from the European Commission (EC) as compatible State Aid. The
procurement process began soon after with the placement of the OJEU
advertisement on 13th June 2005. The deadline for
submission of tenders was 30th September 2005.
Due to a complex negotiation process it is anticipated that a
contract will be awarded in March 2006.
The delays experienced are not expected to impact on the
timescale for rolling-out broadband to sites in the un-served areas
during 2006.
Strategic Target 4
"Issue at least a thousand Business Support Scheme Grants
to SMEs and voluntary sector organisations in Wales"
Progress Review
As part of the Broadband Wales Programme, the WDA launched the
SME Broadband Satellite Subsidy Scheme in September 2002. The aim
was to help businesses take advantage of broadband - as affordable
mass market broadband was only available to 36% of the country at
that time. The subsidy, which had a ceiling of £1500 per business,
was successfully taken up by 250 companies.
In March 2004, following a review, an extended and enhanced
Broadband Business Support Scheme was launched.
The new Scheme included:
- All broadband technologies (ADSL, Wireless, Cable, Leased Lines
as well as Satellite).
- Voluntary sector organisations (as well as small and medium
sized businesses).
- Support of up to £3000 or 50% of first year costs (whichever
was the least) to help eligible organisations access
broadband.
Due to the success of the Scheme, the strategic target
published in the Broadband Wales Programme Strategy for 2005-2007
was achieved in July 2005. By the end of the 2005, over 1200
grant applications had been approved and processed.
In light of the fast changing market conditions – significant
growth in the availability of ADSL broadband and the downward
pressure on all broadband prices - it was decided that the
Broadband Business Support Scheme would close during the first
quarter of 2006; with grant payments being processed up to
31st March 2007.
From a European Commission (EC) State Aid perspective the
Scheme was operated on a 'de minimis' basis.
Strategic Target 5
"Create a fund to support the provision of broadband to
public sector sites in Wales"
Progress Review
The Connectivity Grant Support Scheme (CoGS) to help improve
the provison of broadband to public sector sites across Wales was
not progressed during 2005.
The target was withdrawn because it was not possible to
deliver the Scheme within its project funding timeline due to EC
State Aid constraints on broadband projects.
The Welsh Assembly Government will continue to seek
improvements in the effective procurement and use of high bandwidth
connectivity within the public sector in Wales through the Public
Sector Aggregation (PSBA) project.
Strategic Target 6
"Develop an agreed Welsh policy for the aggregation of
public sector demand for broadband infrastructure"
Progress Review
The Public Sector Broadband Aggregation (PSBA) project is
considered to be a key enabler for delivery of the aims contained
within the Welsh Assembly Government's Making Better
Connections: Delivering Better Services for Wales document.
That document sets out the vision for public services in Wales. The
associated Delivering Better Connections: From Vision to
Action document sets out the 5 year action plan for driving
forward the changes envisaged in how public services are
delivered.
PSBA is seeking to establish the most effective way of
procuring broadband networks. It aims to achieve 'best value'
high-bandwidth connectivity and related services through the
aggregation of demand across the public sector in Wales. This will
facilitate the achievement of more joined-up public services;
offering joint commissioning of services, sharing of support
services across multiple agencies and the development of innovative
delivery models.
The project board has met regularly to review progress and
policy and technical working groups have ensured that stakeholder
requirements and end-user needs are taken into account throughout
the policy development stages. The team has considered strategic,
operational and financial benefits; with a particular focus on
interoperability and collaborative working.
Key milestones achieved during the review period
included:
- Stakeholders engaged and cross-sector working groups
established.
- Consultants contracted (end June) to help stakeholders
determine current needs and future requirements to be incorporated
in the PSBA business case.
- Technical options paper circulated and reviewed regularly to
ensure requirements addressed.
- Public sector network owners (including health and education)
re-aligned key procurement dates to support potential PSBA
outputs.
Before the end of 2005, a paper was tabled for approval at the
Cabinet meeting on 23rd January 2006. The paper outlined
the proposed policy. The minutes and papers of the meeting
(complete or otherwise) are due to be published on the Welsh
Assembly Government website during the week commencing
6th March 2006.
Strategic Target 7
"Demonstrate to the telecommunications industry the level
of demand for second generation broadband infrastructure that
exists in Wales"
Progress Review
This target was not achieved during the review period. The key
findings of a commissioned study, which is due to deliver an
Outline Business Case in May 2006, will be used to inform the
development of policy in this area.
Two factors led to the decision to commission the study:
- Promotional activities undertaken by the marketing team
targeted individuals, businesses and voluntary sector organisations
in the commercially unviable exchange and other potential
'broadband not-spot' areas i.e. areas where it may not be possible
to access first generation broadband. As a result, the Broadband
Brokerage Scheme (www.bbwo.org.uk) -
established in partnership with the Broadband Wales Observatory
(BBWO) - failed to gather robust evidence of the 'un-served' demand
for higher speed broadband.
- Second generation broadband was made available in targeted
geographical areas of Wales. For example, broadband users were able
to access:
- Up to 3Mbps in NTL's South Wales Cable Franchise area i.e. in
the Valleys and along the M4 corridor (NTL began to roll-out its
10Mbps service early in 2006 and announced a 100Mbps trial).
- Up to 8Mbps from targeted telephone exchanges in Cardiff and
Wrexham i.e. exchanges 'unbundled' by Bulldog (the local loop
unbundler owned by Cable & Wireless).
- Up to 8Mbps from targeted telephone exchanges in the Cardiff
area i.e. exchanges selected by BT for commercial trial (BT
Wholesale has confirmed that it will roll-out the service UK-wide
in the Spring of 2006).
The Outline Business Case will:
- Assess the current provision of and demand for second
generation in Wales.
- Assess the expected provison of and likely demand for second
generation broadband across Wales, up to an including 2010.
- Demonstrate the benefits of second generation broadband
provision to Wales in a qualitative and quantitative sense (using
100% availability of first generation broadband as the
counterfactual).
- Based on the above make recommendations about the need for
public sector intervention in the second generation broadband
market and outline the return on investment for Wales of any
interventions proposed.
Strategic target 3, RIBS, is on schedule to be achieved by the
revised deadline date and a study has been commissioned to assist
with the achievement of strategic target 7 (demand for second
generation broadband). Strategic target 5 was withdrawn during the
review period.
[1] Calculation is based on 450,000 broadband
connections in Wales, September 2005
[2] Calculation is based on 9 million broadband
connections in UK, September 2005
[3] ORC Residential Survey – CATI, 5500 interviews,
October 2005
[4] Broadband defined as connection speeds of
512kbps and above
[5] 39% of all respondents had a broadband connection
at home of 128kbps or above, October 2005